A new analysis by market intelligence firm Sightline Climate reveals that nearly 50% of US data centers scheduled to open in 2026 are facing significant delays or outright cancellation. Of the 12 gigawatts of planned capacity, only 4 GW are currently under construction, with electrical supply chain bottlenecks identified as the primary blocker.
The core issue lies in critical electrical components — transformers, batteries, switchgear, and circuit breakers — many of which are manufactured in China, Canada, Mexico, and South Korea. While these parts account for less than 10% of total construction costs, they are essential chokepoints that can stall entire projects. "If one piece of your supply chain is delayed, then your whole project can't deliver. It is a pretty wild puzzle," said Andrew Likens of Crusoe Energy.
The situation is expected to worsen in 2027, when only 6.3 GW of the 21.5 GW announced is under construction. This comes despite Alphabet, Amazon, Meta, and Microsoft planning to spend over $650 billion in 2026 to expand AI capacity, highlighting a growing gap between investment ambitions and physical infrastructure reality.